WATER HAMMER IN STEEL TRUNK WATER CONDUITS AND PROTECTION MEASURES (CASE OF THE KAMPIRRAVAT – FERGANA SYSTEM)

Authors

  • Raxmankulov Salimjon Azamdjanovich Independent Researcher Research Institute of Irrigation and Water Problems, Tashkent, Uzbekistan

Keywords:

Water hammer, wave celerity, steel pipe, valve closure time, relief valve, expansion joint.

Abstract

Water hammer is analysed in the steel gravity conduit (Kurgantepa – Fergana, 1020×9 mm) and the pumped conduits (Fergana – Pakana and Fergana – Kirguli, 820×8 mm) of the Kampirravat – Fergana water transfer system. The pressure wave celerity is calculated with Joukowsky's formula and compared for different pipe materials. In steel pipes the celerity is 980–1006 m/s, 2.4–2.5 times higher than in glass-fibre reinforced plastic pipes. Rapid valve closure on the Kurgantepa – Fergana conduit raises the pressure by 175 m to a maximum of 336 m, i.e. 1.9 times the allowable value of the pipe. The minimum permissible valve closure times are determined for each section (42–119 s), and 200–240 s is recommended in practice. The filling regime of the conduit and the number of air valves are determined. Protection devices for the pumping stations and temperature compensators for above-ground sections are justified. Steel and GRP pipes are compared in terms of surge head, allowable pressure and resistance to vacuum.

Downloads

Published

2025-11-30

Issue

Section

Articles

How to Cite

WATER HAMMER IN STEEL TRUNK WATER CONDUITS AND PROTECTION MEASURES (CASE OF THE KAMPIRRAVAT – FERGANA SYSTEM). (2025). European Journal of Interdisciplinary Research and Development , 45, 468-475. https://ejird.journalspark.org/index.php/ejird/article/view/2312